Azerbaijan:
Feasibility Study for Absheron Wind Farm Projects with Photovoltaic Component

Azerbaijan founded the "State Agency on Alternative and Renewable Energy Sources - ABEMDA" (later AREA) to improve the conditions for investments in new generation capacities. KfW provided a loan for the implementation of a "flagship" renewable investment project - the Absheron Wind Farm. The scope of the study was later extended to include also the integration of PV components. The project prepared feasibility studies for two potential sites.


Services
  • Analysis of electrical data, network and short circuit calculations (PowerFactory) and grid connection concepts
  • Technical specifications for the main electrical grid connection equipment
  • Clarification of legal situation of PPA (power purchase agreements) for independent power producers
     
Technical Data
  • Xixi site: 21 wind turbine generators (WTGs) of 3.3 MW each; 35 kV infield connection; 10 MW PV generation; new 110 kV single-circuit line (15 km) up to an existing 330/220/110 kV substation 
  • Qaradag: 16 WTGs of 3.3 MW each, 35 kV loop infield connection; 10 MW PV generation; new 110/35 kV substation, new 110 kV double-circuit OHL of 10 km length
     

Client:
Ministry of Economic Development (MOED)
Financing:
KfW Development Bank
Period:
2012 - 2017